XXXX Brewery

Central Scaffolding provided 55 tonne of Layher scaffold for the project, which we would consider to be a small scale job.

  • Date: Ongoing client
  • Client: Castlemaine Perkins
  • Project Type: Shutdown

About this Project

Located in Milton, Brisbane, the Castlemaine Perkins brewery required scheduled inspections and new installations of equipment. Central Scaffolding provided 55 tonne of Layher scaffold for the project, which we would consider to be a small scale job.

The workers were able to relag and inspect the fermenting tanks, install new equipment, and perform any necessary repairs to ensure optimal operation of the brewery.

    Maintenance Scaffold Work Milton Queensland

    This project was completed in approximately 4 months with the scaffolding removed from site in just three days.

    The team carefully designed this project every step of the way allowing us to complete the project on time, in budget and with zero incidents.